Large electrical load projects
As the Sacramento region grows, so does energy demand. We’re proactively planning for that growth responsibly, with you in mind. We’re committed to providing our customers and community with safe, reliable, affordable and clean electricity.
Some of the growth in demand comes from large customers who require a lot of energy, including manufacturing and data centers. And while national headlines often focus on large-scale data center growth, the situation in the Sacramento region is a little different.
Our FAQs include answers to common questions about what we see locally, how requests to connect large electrical loads to our grid are reviewed and how we're protecting affordability and reliability for our community.
Are you interested in learning more? We're holding a virtual forum where you can learn more and share your thoughts.
Large Electrical Load Projects Virtual Forum
Aug. 13, 5:30 to 6:30 PM
The virtual forum will be hosted via Zoom with a capacity of 1,000 participants. We know your time is valuable. As a thank you for joining us, all attendees will be entered into a drawing for a chance to win 1 of 5 Amazon gift cards valued at $100 each. View official rules
Let us know you're coming
Get meeting details and a reminder sent straight to your inbox.
Frequently asked questions
We've served large energy users in the region for many years. Our established processes help evaluate projects, plan service and protect existing customers from costs tied to infrastructure needed to support new growth. Along the way, we continue to support business investment and regional economic development while helping ensure the cost of serving a new large electrical load customer is not shifted onto existing customers.
A large electrical load customer is simply a very big electricity user. We generally consider this to be 50 megawatts or more, because a customer that size is served by our high-voltage transmission system. Most of our largest customers to date have topped out around 20 megawatts, so newer data-center inquiries at 50 megawatts represent a bigger scale than we have historically served.
Large electrical load projects require more planning, engineering and infrastructure than typical commercial development.
No. Data centers have operated in our region since around 2000, and more than a dozen are here today. They support everyday services that our region relies on - banking, hospitals, telecommunications and technology.
What’s new is the larger, AI-driven type that provides computing power.
We do not make land-use decisions. They’re made by local city and county governments through their own public environmental approval processes. Community questions about things like land, water and neighborhood impacts are decided there. Our role is restricted to providing electricity for approved projects.
Once a local jurisdiction approves a project, we have an obligation to serve it with electricity – the same obligation we have to any approved customer in our service area.
We engage early. Because available capacity is not the same across our service area, some locations are better suited than others for large electrical load customers. Our dedicated commercial development team walks large projects through the process, and every large customer project starts with a transmission study to understand costs and impact on the grid before anything moves forward. These projects take time and careful planning – they don’t happen overnight.
We have a process for extending service and assigning related costs to current large customers to help protect existing customers.
To ensure new large electrical load customers are handled consistently, we are working on a new policy for customers 50 MW and above with the goal of protecting existing customers from cost shifts from these new larger customers.
Yes. Some large electrical load customers can reduce or shift their energy use during peak-demand hours. That flexibility lowers the amount of power we have to buy at the most expensive peak times while generating new revenue, which helps keep rates low for everyone. Large businesses also create jobs and boost local economic development.
We’re planning ahead. We're developing a large-load policy – expected to go to our Board of Directors later this year. It will detail how we’re protecting affordability and reliability for all customers. As part of our broader planning for regional growth, we're also investing roughly $600 million in substation upgrades to maintain reliable service while keeping rates among the lowest in California.
As a community owned, not-for-profit electric service, we answer to the people we serve. We’ll keep putting customers first – growing responsibly while protecting the affordable, reliable, world-class service our community deserves.