Global supply chain delays are impacting SMUD’s ability to purchase equipment, including some types of transformers, resulting in longer lead times. We’re doing everything possible to mitigate the impacts this may have on your construction project.
SMUD will apply these criteria to distribute transformers impacted by supply chain shortages to minimize the impact to as many projects as possible. In general, when there’s a shortage of a specific type of transformer, or other equipment, SMUD will issue available transformers and equipment once the customer’s project is electrically ready to serve load. We’ll issue the transformers to customers based on the date of electrical readiness, per specific field conditions. See detailed transformer distribution criteria.
Design & Construction Services
Whether you're adding an electric vehicle charger or building your dream house or a sports arena, our Design & Construction Services team is here to help you connect to SMUD's electric system.
Getting started
- Get more information about the application and connection process for a new construction, upgrade or remodel project that will need more than a meter installation and connection of electric service.
- If you need new service or an upgrade to existing service that won't require upgrades or additions to SMUD's existing infrastructure, review our meter and service only guidelines.
-
Planning to build an accessory dwelling unit or secondary dwelling? Refer to our planning tips to help avoid redesign costs and project delays.
Please note: Each local agency has its own requirements for construction projects. We suggest that you discuss your project with the appropriate agency before submitting your project application to us. Contact your local agency for more information about their requirements.
Please choose your desired process and get a detailed description of each:
- New SMUD construction required
- Meter and service
- Local agency ABC
- Macro cell site application
- Small cell site application
- Downtown commercial
Please remember to call 811 or visit www.Call811.com before you dig.
Criteria for issuing equipment impacted by global supply chain constraints
Global supply chain shortages and delays are impacting a variety of products, including transformers and other equipment needed for construction and development projects. In fact, due to the impact to electric utility critical infrastructure, President Biden issued Presidential Determination No. 2022-19 in June to expand domestic production capability for transformers and electric power gird components. While SMUD continues to do everything possible to minimize the impact to our customers, their projects and our operations, like all other utilities, we’re seeing delivery shortages and much longer lead times for certain types of transformers. It means there will be times when we can’t provide transformers to construction and development projects in line with our normal process and timeline, due to lack of stock.
SMUD will apply the following criteria to distribute transformers impacted by supply chain shortages to minimize the impact to as many projects as possible. In general, when there’s a shortage of a specific type of transformer, or other equipment, SMUD will issue available transformers and equipment once the customer’s project is electrically ready to serve load. We’ll issue the transformers to customers based on the date of electrical readiness, per specific field conditions.
Once SMUD confirms electrical readiness, available equipment will be issued in accordance with our normal construction process.
The criteria also includes a process for getting into the queue to receive out-of-stock equipment once SMUD receives additional deliveries.
For commercial development projects (excluding subdivisions)
SMUD will issue available transformers once payment is made, construction is significantly underway and the project is electrically ready. Specifically, for commercial development projects, electrical readiness means:
- The electrical panel and conductor are onsite
- For projects with buildings, the foundation and framing are complete
- For electric vehicle chargers, water pumps, cell sites and similar projects, all equipment using the load (e.g., the charger, pump or tower) is onsite
If transformers are out of stock, SMUD will place the project in the queue to receives the transformer(s) based on the date of electrical readiness. We will provide the customers with an estimated date of delivery, based on the latest delivery dates provided by the supplier. Please note that these dates are subject to change. If the availability date changes based on information from the supplier, SMUD will advise the customer of the change and the new estimated delivery date.
For subdivisions
SMUD will issue available equipment once payment is received and the subdivision has lots that have passed their framing inspection, as confirmed by SMUD. Specifically, SMUD will check for:
- Subdivision improvements are completed (roads are installed, paved)
- Framing inspection is complete
Once SMUD confirms readiness, two transformers will be issued to each of the subdivision’s developers based on the date when the subdivision became ready. This will enable energization for model home sales and field office activities. This process will continue until all available transformers are assigned to developers.
Once additional transformers become available, they’ll be assigned on a rotational basis, one at a time, starting with the next developer in the queue until all the transformers are assigned.
When a new subdivision becomes electrically ready, it will move to the front of the queue for developers to each receive the first two transformers. After each developer received their first two transformers, the subdivision then becomes part of the rotational process to assign additional transformers, one by one, as they become available.
Prior to transformer delivery, SMUD will ask developers to provide a prioritized list of transformer locations. SMUD will run all cable at the beginning of the job. As transformers are delivered, they will be installed on the pads in the priority order specified by the developer.
Process for confirming electrical readiness
This process applies to commercial development projects and subdivisions.
Once a project has reached the applicable electrical readiness milestones above, contact SMUD’s Commercial Development & Solutions team at development@smud.org or 1-916-732-5448. We'll inspect the project to confirm electrical readiness. When electrical readiness is confirmed, equipment will be issued in accordance with our normal construction process.
For projects deemed to be not electrically ready, we’ll advise customers of the readiness criteria and ask them to contact SMUD once the criteria are met. We’ll reach out to these customers periodically to re-evaluate readiness. Once the project reaches electrical readiness, it’ll be placed in the queue for equipment distribution based on the date SMUD was able to confirm electrical readiness.
For more information, contact SMUD’s Commercial Development & Solutions team at development@smud.org or 1-916-732-5448.
- Customer-Built Vaults – Engineering Specification T001: Aug. 2021
- Residential Overhead – Engineering Specification T002: Aug. 2024
- Residential Underground – Engineering Specification T003: Mar. 2021
- Commercial Industrial – Engineering Specification T004: Nov. 2022
- Customer Owned Service Poles – Engineering Specification T005: Oct. 2018
- Agricultural Pumps – Engineering Specification T006: June 2017
- Distribution Underground Structure – Engineering Specification T007: Nov. 2022
- 69kV Underground Structure – Engineering Specification T008: Jan. 2020
- Transmission 69kV Service – Engineering Specification T010: Jan. 2020
- Macro Cell Antenna Installations on SMUD Facilities - Engineering Specifications T012: Oct. 2018
- Customer Owned and Constructed Transformer Enclosure – Engineering Specification T013: Jan. 2020
- Residential Distributed Generation – Engineering Specification T014: Oct. 2024
- Commercial Distributed Generation – Engineering Specification T015: Jan. 2020
- Small Cell Antennas on SMUD Distribution Poles - Engineering Specification T016: June 2020
- Commercial Electric Vehicle Program - Engineering Specification T017: Mar. 2018
Questions?
Our Design & Construction Services team is here to help you every step of the way.
Email: Design.Construction@smud.org
Phone: 1-916-732-5700
Additional information
- Addressing Guidelines for Multi-Unit Buildings
- SMUD Real Estate Services
- Transmission rights and consent to common use
- Integrated Design Solutions: A construction incentives program encouraging energy efficiency and electrification in new and extensively renovated commercial buildings
- Photovoltaic interconnection information
- Report a street light outage
- SMUD rates
- SMUD rules and regulations