2026 Transmission Pole Maintenance
To ensure reliable service, we’re performing maintenance on six transmission utility poles, which includes:
- Removing surface corrosion and applying new protective coatings
- Deenergizing distribution lines during repairs for safety; power will be rerouted to prevent interruptions
Location
The poles are located behind SMUD Headquarters along the Sac RT Gold Line between 59th and 69th Streets, near the Home2 Suites and Hampton Inn & Suites parking lots.
Community considerations
Some surface preparation work involves cleaning poles or blasting down to bare metal. Some overspray could extend outside of the immediate work area.
Timeline
Mitigation activities occur Oct. – Nov. 2026, 7 days a week, 6 a.m. to 6 p.m.
The work is completed in two phases:
- Phase 1 – Oct.19 - Nov. 1
- Location / customer impacts (i.e. sidewalks will be closed at XYZ location)
- Phase 2 – Nov. 1 - 15
- Location / customer impacts (i.e. sidewalks will be closed at XYZ location)
Our contractor, F.D. Thomas, performs the maintenance work with our SMUD inspectors onsite monitoring the repairs.
We’re committed to keeping the community informed about this project and will update this page with project status and schedule information.
Questions?
For questions about this project, email Max.Katkanov@smud.org.