Nueva construcción de SMUD requerida

1

How to apply

Pre-application requirements

Here are the three things you need to do before submitting your project application to SMUD.

Contact local agency

Each local agency has its own requirements for construction projects.

Submit your project plans to local agent

Once you've met local requirements submit your project plan to the appropriate authority.

Obtain a "plan check" number.

After receiving your project plan the local agency will issue you a "plan check" number.

Note: you will need this number to submit your application to SMUD.

Enviar solicitud a SMUD

Ahora está listo para entregar su formulario de solicitud, los documentos requeridos y las tarifas a SMUD. El envío puede hacerse en línea, por correo postal o en persona.

En línea

Pague de manera electrónica mediante el sitio web Project Application. Ingrese a su proyecto con su número de Notificación de Servicio de SMUD y siga las instrucciones que aparecen en línea.

Correo postal

SMUD
Design & Construction Services
P.O. Box 15830, MS EA-105
Sacramento, CA 95852-0830

En persona

SMUD
East Campus Operations Center
4401 Bradshaw Road
Sacramento, CA 95827


2

Meet your designer

SMUD will assign an engineering designer for your project, typically within five days after receiving your application.

Your engineering designer will:

Connect

Be your main point of contact for your project

Plan

Address your project's electrical requirements and construction schedule

Assess

Determine if civil improvements are needed before SMUD construction can begin

Need civil improvements?

Civil improvements may include trenching and installing conduit,
boxes and pads for SMUD’s electrical cable and equipment.

If civil improvements are required:

Your SMUD engineering designer will provide you with a Commitment Package that explains the requirements and your responsibilities.

You'll need to schedule a pre-construction meeting with a SMUD inspector, who will provide direction for your installation of the required civil improvements.

All civil improvements must be completed before SMUD can begin actual construction of your project.



3

Return required construction
documents to SMUD

This is a critical step in the process to keep
your project on schedule.

Avoid delays

To avoid project delays, please return all required documents as soon as possible.

Remember:
Make sure all
documents are
complete before
submission.

Documents you'll need to submit

Your engineering designer will tell you what documents must be submitted
before SMUD can begin construction of your project. These may include:

SMUD's
agreement to
grant easement
Conveyance
agreement
Copies of
your property
grant deed
Building
permits

4

Time to go to work!

Once all required documents are submitted and approved, your engineering designer will complete the final job design and determine the cost of the work.

Contract and
payment letter

You will receive a project quote
and contract letter from SMUD.
It will include instructions for
approving the contract and
making a payment.

Here's what happens next

Schedule

After we receive your approval contract, any required fees, and after all other holds have been removed, SMUD will schedule construction of your project. You will be notified by email that the job is progressing to construction.

Construction

SMUD's construction work is performed. This includes all electric facilities and equipment except the meter, which will be installed after the panel is inspected by your local agency.

Inspection

Your local agency must inspect and approve your electrical panel before SMUD completes its work. Local agencies typically notify SMUD one business day after they approve the work.

Power on!

SMUD will install the new meter, connect or install the service wire and energize your service, typically within seven business days of the electrical panel inspection approval.