Station E substation

The Station E substation will improve the reliability and capacity of midtown and downtown. 

 Aerial map of the location of the station E substation
Click for larger view of map

SMUD is constructing a new substation in Sacramento at the north end of 20th Street, north of C Street and the Union Pacific Railroad tracks. The new Station E Substation will replace the North City Substation. Constructed in the 1950s, the North City Substation is nearing the end of its planned operational use.

Substations are critical links in the electrical distribution system. Electricity travels through SMUD’s transmission system to substations where it can be converted to a lower voltage before safely being delivered to homes and businesses. The Station E Substation will directly serve the midtown and downtown areas, improving energy reliability and capacity.

Anticipated activities

The scope of work for Final Construction includes:

  • Grading and surfacing
  • Construction of concrete foundations and control building

 Installation of:

  • Underground conduit and grounding
  • Steel structures and equipment (transformers, circuit breakers, switches)
  • Electrical buss and wiring
  • Testing and commissioning
  • Cutover of overhead and underground transmission and distribution lines from the existing North City Substation

Environmental enhancements and management

Environmental leadership is one of SMUD’s core values. SMUD has invested over $16 million to haul away waste and contamination that had been on the site for decades to prepare it for substation construction which begins May 2019. 

The portion of the site where Substation E will be constructed is now much cleaner and safer and meets environmental and geotechnical requirements for construction.

Learn more about the project site and view original CEQA documents.

Learn who will remove the waste and how it will be removed.

Questions?

Call us at 1-916-732-5715 or email us at StationE@smud.org with your questions or comments.

Additional information

SMUD and its construction contractor will monitor air quality during substation construction keeping an eye on dust emissions from the site. Air quality monitoring data will be made available here and updated once a week.

View current air monitoring report     Get weather conditions

For previous air quality reports, please email StationE@smud.org.

Learn how to reduce your exposure and protect your health from harmful particle pollution.

SMUD’s contractor is required to implement dust control measures that include the following:

  • Wetting travel areas with water trucks
  • Stockpile management BMPs
  • Onsite speed limit
  • Limited soil disturbance during high winds
  • Dust monitoring
  • Track out control measures
  • Wet power vacuum street sweeping

September 2019 Update

The project continues moving forward, the main focus continues on preparation of the site for winter rains. The primary work planned now and into October/November consists of completing the following:

  • Construction of remaining piers (currently 70% complete) and installation of steel structures. Much of the steel is on site and several structures were erected the week of 9-9-19 as shown below.
    Picture of station E progress, bulldozers and tractors

  • Construction continues with the ~10,000 sqft, 2 story Control Building. The completion of the shell is a key component to allowing work to continue during the rains. We anticipate going to 6 days per week work (adding Saturdays) for the next few months. The picture below shows scaffolding in-place and block wall being installed by skilled masons.

Picture of station E construction progress

Other Items:

  • Preparation for underground work near the UPRR tracks began.
  • Transformer pad foundations are under construction in preparation for the move in of several transformers. These transformers are planned to move to the site in late October.
  • Additionally, over 32,000 lbs of aggregate base rock will be placed, to bring the site to “near final grade” before the rains. Much of this material is planned to be sourced from Bell Marine’s site to minimize traffic in the neighborhood.

Project status archive

Sign up below to receive Station E updated via email or mail.