Clean up, construction and haul route

Clean up

SMUD plans to safely remove the hazardous waste and resume substation construction. Cape Environmental Management has been awarded a waste removal contract that includes the following activities:

  • Excavation, removal and disposal of up to 64,000 tons of unacceptable soil and debris
  • Processing and compaction of acceptable soil
  • Import and compaction of clean fill

Waste removal and clean-up is expected to take place from March 2018 through September 2018.

Haul route

We have identified a haul route that will minimize impact to nearby neighborhoods.

Two types of vehicles will be primarily used for waste removal. Truck haul hours are tentatively scheduled for 7:30 am to 5:00 pm

Map of haul route with arrows for fill trucks and waste trucks
View detailed map of haul route